Agilent Technologies J3972A Guía de usuario Pagina 127

  • Descarga
  • Añadir a mis manuales
  • Imprimir
  • Pagina
    / 551
  • Tabla de contenidos
  • MARCADORES
  • Valorado. / 5. Basado en revisión del cliente
Vista de pagina 126
Reporter
Scheduling Reports
126 5967–9446
To schedule on one day per week
1 Click or choose ReportSchedule/Output Setup…
2 Select Generate Report Weekly.
3 Select the day of the week and indicate the time.
To generate a report once per week, use the weekly schedule option,
shown in figure 20.
Figure 20 Schedule: Weekly
Choose Weekly
Select the day and
specify the time
This example schedules the report each Sunday at 11:45 pm.
Vista de pagina 126
1 2 ... 122 123 124 125 126 127 128 129 130 131 132 ... 550 551

Comentarios a estos manuales

Sin comentarios